| The Ohio Department of Natural Resources has initiated an aggressive improvement program to upgrade the trail and bridge system within the park. |
 |
 |
Flash flood damages trails and bridges |
January 7, 1998 |
 |
 |
Trail maintenance and temporary repairs by Civilian Conservation Corps and State Parks Construction Crews |
Completed May 1998 |
 |
 |
Upgrade Access to Gorge Overlook Trail by Civilian Conservation Corps and State Park Construction Crews |
Completed May 1998 |
 |
 |
Construct temporary bridges at Old Man's Cave and Lower Falls by Civilian Conservation Corps |
Completed July 1999 |
 |
 |
Damage assessment and preliminary planning by ODNR and consulting engineers/architects, ms consultants, inc. |
Completed January 1999 |
 |
 |
Construct new stairs for Gorge Overlook Trail at Cedar Falls by Civilian Conservation Corps |
Completed January 1999 |
 |
 |
Design and complete trail redevelopment, including construction of new bridges: |
|
 |